Analysis of Causative Factors of Delayed Project Completion (Case Study of Norfa Husada Mother and Child Hospital)
DOI:
https://doi.org/10.31004/jestm.v6i1.352Keywords:
Project Delay, Dominant Factors, Construction Management, Norfa Husada HospitalAbstract
Construction project delay is a condition where the execution of work does not proceed according to the agreed schedule. The construction project of Norfa Husada Mother and Child Hospital experienced delays impacting costs and operational time. This study aims to identify the factors causing delays, determine the most dominant factors, and formulate preventive measures. The method used was a questionnaire distribution to 30 respondents directly involved in the project, including contractors, consultants, and project owners. Data were analyzed using descriptive statistics (Mean Rank) with SPSS software. The results show that the Planning Factor is the most dominant cause, specifically due to design changes (redesign) and changes in the scope of work, with a mean value of 1.97. The second dominant factor is the Execution Factor, particularly regarding poor work sequence planning, with a mean value of 1.90. Based on these results, the main strategies to prevent delays include maturing the design planning before construction begins, strengthening coordination between the owner and contractor regarding scope changes, and establishing a more structured method of execution (SOP) in the field.
References
Badan Standardisasi Nasional. (1990a). Metode Pengujian Kadar Air Agregat. In Badan Standarisasi Nasional.
Badan Standardisasi Nasional. (1990b). SNI:1968-1990 Metode Pengujian Tentang Analisis Saringan Agregat Halus. In Sni 03-1968-1990.
Badan Standardisasi Nasional. (1997). SNI 4428-1997 Metode Pengujian Agregat Halus atau Pasir yang Mengandung Bahan Plastik Dengan Cara Setara Pasir. In Bandung: Pusjatan Balitbang.
Badan Standardisasi Nasional. (2014). SNI 8319-2016Metode uji bahan organik dalam agregat halus untuk beton.
Badan Standardisasi Nasional. (2016). SNI 1970-2016 Metode Uji Berat Jenis dan Penyerapan Air Agregat Halus.
Badan Standardisasi Nasional. (2018). SNI 8640-2018 Spesifikasi bata ringan untuk pasangan dinding.
Badan Standarisasi Nasional. (1996). Metode Pengujian Jumlah Bahan dalam Agregat yang Lolos Saringan No 200 (0,075 mm). In Sni 03-4142-1996 (Vol. 200, Issue 200).
Desember, V. N., Rahman, F., & Belakang, L. (2017). Kata kunci: limbah cangkang kelapa sawit, pengganti pasir, beton normal. 6(1), 30–40.
fadli eka. (2020). Pengaruh Penambahan Abu Cangkang Kelapa Sawit Terhadap Karakteristik Beton Mutu Tinggi.
Haryanti, N. H., & Wardhana, H. (1994). Pengaruh Komposisi Campuran Pasir Silika dan Kapur Tohor Pada Bata Ringan Berbahan Limbah Abu Terbang Batubara.
Latjemma, S. (2021). Pengaruh sumber material agregat halus sebagai bahan campuran terhadap kuat tekan beton normal. 16(1), 6035–6048.
Negeri, M., Belitung, B., & Maulana, D. H. (n.d.). No Title.
Ningrum, D. K., & S., M. F. (2018). Pengaruh penggunaan kapur sebagai bahan pengganti sebagian semen terhadap berat volume, kuat tekan dan penyerapan air pada bata beton ringan seluler berbahan dasar. Rekayasa Teknik Sipil, 3(Clc), 1–8.
Noprian, P. (2021). Pemanfaatan Abu Sekam Padi Sebagai Substitusi Semen Pada Bata Ringan. Paulus Civil Engineering Journal, 3(4),–621. https://doi.org/10.52722/pcej.v3i4.341
Rahmawati, C., Handayani, L., Silika, S., Abu, D., & Padi, S. (2019). Pendahuluan Memanfaatkan material alam pada bidang konstruksi akan mampu menjaga lingkungan . Material alam ini dapat dijadikan bahan subtitusi semen , diketahui bahwa semen dalam produksinya menyebabkan emisi rumah kaca . Produksi gas CO 2 terjadi pada s.5(2),164–175. https://doi.org/10.22373/ekw.v5i2.5533
SNI 7656:2012. (2012). Tata Cara Pemilihan Campuran untuk Beton Normal, Beton Berat dan Beton Massa. In Tata cara pemilihan campuran untuk beton normal, beton berat dan beton massa.
Syahrial, M. (2022). Kelebihan dan Kekurangan Bata Ringan atau Hebel (M. Syahrial (ed.)). Kompas.com.
Vitri, G., & Herman, H. (2019). Pemanfaatan Limbah Kelapa Sawit Sebagai Material Tambahan Beton. 6(2), 78–87. https://doi.org/10.21063/JTS.2019.V602.06
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Gerry Thoriq, Beny Setiawan, Lailatul Syifa Tanjung

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.